Fri 04 Jul 2025

Site progress update!

Site progress update!

Check out the latest developments at the Ham Hill Visitor Centre!

Key highlights of the progress include;

•    Completion of all external wall timber framing 

•    Installation of all posi-joists 

•    Progression of roof decking and related timber work

•    Installation of the Integrated Lintels

•    Excavation of the Klargester tank hole and placement of the concrete slab  

•    Installation of service ducts around the building and drainage systems 

We are pleased to see the project evolving on site as the construction stage progresses.

 

Photography courtesy of Martin Cooke, Heritage & Leisure 

Saunders Boston Architects

Follow us on LinkedIn and Instagram for updates on the latest exciting projects...